July 11th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
BUILDING ENVELOPE
ROOF
Install roof drains
Install insulation and TPO on Main Roof
Coping and final metal work
FACADE
Install windows
Install AVB and secondary window flashing
Install masonry facade
INTERIOR CONSTRUCTION
Pre weather tight mechanical, electrical, plumbing, and fire protection rough installations at all levels
Layout and frame interior partitions at levels 4 &5
UPCOMING ACTIVITIES
Utility work on Regent Street anticipated for the last week of July
TRUCKING/DELIVERIES
Window delivery anticipated 7/18/2022