June 22nd Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
STRUCTURAL WOOD FRAMING
Install 5th-floor walls and roof trusses
BUILDING ENVELOPE
Install roof drains
Install insulation and TPO on Main Roof
INTERIOR CONSTRUCTION
Layout and frame interior partitions
Fire Protection and HVAC rough installations and electrical layout on all floors
Construct CMU elevator shafts
UPCOMING ACTIVITIES
*Eversource work of Dabney Street expected to be complete by the end of 6/22 allowing for the reopening of Dabney Street
TRUCKING/DELIVERIES
We are scheduled to have frequent wall panel deliveries upcoming and a large crane will be onsite for approximately the next 30 days.