June 9th Construction Update

 
 

Summary Of Activities:

SITEWORK/MOBILIZE CONSTRUCTION SITE

(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)

SITEWORK/UTILITIES

  • Retaining wall install

  • Install stormwater drainage systems

STRUCTURAL WOOD FRAMING

  • Install 5th-floor walls and roof trusses

INTERIOR CONSTRUCTION

  • Layout and frame interior partitions

  • Fire Protection and HVAC rough installations and electrical layout on the 2nd floor

  • Garage fire protection system (dry)

  • Construct CMU elevator shafts

UPCOMING ACTIVITIES

*Street closures are forthcoming in the next couple of weeks. Specific dates and streets will be provided with next week’s construction update.

TRUCKING/DELIVERIES

We are scheduled to have frequent wall panel deliveries upcoming and a large crane will be onsite for approximately the next 30 days.

Previous
Previous

June 22nd Construction Update

Next
Next

May 24th Construction Update