December 14th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
LOGISTICS ON FOUNTAIN STREET PER THE CITY OF BOSTON
Strip and dispose of topsoil (Ongoing activity. Will continue past blasting as we work in different areas of the site)
Blasting (Ongoing activity for the next 2 weeks)
Export blasted ledge material (Ongoing activity through blasting and until the beginning of January)
Foundation start date (12/21)
Pour lean concrete for footings
Form footings & walls for concrete
TRUCKING/DELIVERIES
During the activities above, trucking for offloading of soil/ledge will continue. We will have trucks ready to load and remove the soil/ledge in the morning and will be coming and going throughout the day. Both topsoil removal, as well as the blasting, require increased trucking during the day. We continue to operate between 3-4 trucks per day, completing 3 trips.