December 6th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
LOGISTICS ON FOUNTAIN STREET PER THE CITY OF BOSTON
Strip and dispose of topsoil
Ongoing activity. Will continue past blasting as we work in different areas of the site
Layout for blasting and drilling of test holes (12/6)
Test blast (12/08)
Start blasting (12/9)
TRUCKING/DELIVERIES - During the activities above, trucking for offloading of soil/ledge will start. We will have trucks ready to load and remove the soil in the morning and will be coming and going throughout the day. Both topsoil removal, as well as blasting, will require increased trucking during the day. We currently are operating between 3-4 trucks per day, completing 3 trips.