Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
LOGISTICS ON FOUNTAIN STREET PER THE CITY OF BOSTON
Strip and dispose of topsoil (week of 11/22)
Monday delay due to rain. Activity will start Tuesday, 11/23
Wednesday, 11/24 will be the first day trucking the soil offsite
WE ARE OFF THURSDAY (11/25) AND FRIDAY (11/26). HAPPY THANKSGIVING!!
Layout for blasting (12/7)
Start blasting (12/9)
TRUCKING/DELIVERIES - During the activities above, trucking for offloading of soil/ledge will start. We will have trucks ready to load and remove of the soil in the morning and will be coming and going throughout the day