November 22nd Construction Update

 
 

Summary Of Activities:

SITEWORK/MOBILIZE CONSTRUCTION SITE

LOGISTICS ON FOUNTAIN STREET PER THE CITY OF BOSTON

  • Strip and dispose of topsoil (week of 11/22)

    • Monday delay due to rain. Activity will start Tuesday, 11/23

    • Wednesday, 11/24 will be the first day trucking the soil offsite

    • WE ARE OFF THURSDAY (11/25) AND FRIDAY (11/26). HAPPY THANKSGIVING!!

  • Layout for blasting (12/7)

  • Start blasting (12/9)

    TRUCKING/DELIVERIES - During the activities above, trucking for offloading of soil/ledge will start. We will have trucks ready to load and remove of the soil in the morning and will be coming and going throughout the day