May 1st Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
INTERIOR CONSTRUCTION
Appliances install
Owner and Architect punch list is ongoing in some units
SITEWORK
New sidewalks have ben poured on on Fountain Street
Plantings are being installed and will be complete by 4/11/23
Fencing re-work along Regent Street will take place the week of 5/8/23
The parking lot and driveway are being paved Friday 5/5/23 and striped 5/8/23
Temporary fencing along Fountain Street will be taken down once a Certificate of OCcupancy is received for the building
FINAL INSPECTIONS
Boston Fire Department Lights Out Testing is on Wednesday 5/11/23. Once complete and signed off, we can test Fire Alarm, Standpipe, and Life Safety. Once all testing is complete and signed off we can apply for a Certificate of Occupancy.