April 6th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
INTERIOR CONSTRUCTION
Power and water are on in the building
Priming and painting finish coats
Cabinet/Countertop Install
Elevator Install
Appliances install
Owner and Architect punchlist is ongoing in some units
SITEWORK
New sidewalks on Fountain Street are being poured tomorrow 4-7–23. Temporary fencing along Fountain Street will be taken down once the sidewalks have cured
Front paver install – Will take place during the week of 4–10–23
Landscaping and plantings will be installed during the week of 4-17-23