March 9th Construction Update

 
 

Summary Of Activities:

SITEWORK/MOBILIZE CONSTRUCTION SITE

(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)

BUILDING ENVELOPE

  • Install exterior lights

  • Final punchlist activities ongoing

INTERIOR CONSTRUCTION

  • Set permanent power

  • Priming and painting finish coats

  • Flooring install

  • Cabinet/Countertop Install

  • Elevator Install

  • Install Mech/Elec/Plumb finishes

SITEWORK

  • Fencing contractor is back on site 3/10 to finish the perm black chain link fence. Temp has been removed except for Fountain Street.

  • Install site lighting - ongoing. Expect to be complete by 3/17

  • Form and pour Fountain Street sidewalks – Targeting to start work in the next few weeks

  • Front paver install – Targeting March 2oth to begin this work

  • Landscaping and planting - May 1, 2023