March 9th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
BUILDING ENVELOPE
Install exterior lights
Final punchlist activities ongoing
INTERIOR CONSTRUCTION
Set permanent power
Priming and painting finish coats
Flooring install
Cabinet/Countertop Install
Elevator Install
Install Mech/Elec/Plumb finishes
SITEWORK
Fencing contractor is back on site 3/10 to finish the perm black chain link fence. Temp has been removed except for Fountain Street.
Install site lighting - ongoing. Expect to be complete by 3/17
Form and pour Fountain Street sidewalks – Targeting to start work in the next few weeks
Front paver install – Targeting March 2oth to begin this work
Landscaping and planting - May 1, 2023