January 30th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
TRUCKING/DELIVERIES
Minor deliveries will be ongoing
BUILDING ENVELOPE
Install lower and upper cornices
Install masonry at Fountain st elevation
Install Hardie panels at lower profiles
INTERIOR CONSTRUCTION
Drywall install and taping/sanding
Priming and painting
Flooring install
Cabinet/Countertop Install
Elevator Install
SITEWORK
Install permanent black chain-link fencing around perimeter of sight -
Set an of polls around the property to be completed by end of day 1/31.
The actual chain-link fence to begin being installed this week, installation will be about one week.
Install site lighting - February
Form and pour Fountain Street sidewalks – March
Front paver install – March
Landscaping and planting - May 1, 2023