January 10th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
TRUCKING/DELIVERIES
Minor deliveries will be ongoing
BUILDING ENVELOPE
Install lower and upper cornices
Install masonry at Fountain st elevation
Install Hardie panels at lower profiles
INTERIOR CONSTRUCTION
Drywall install and taping/sanding
Priming and painting
Flooring install
Cabinet Install
Elevator Install
SITEWORK
Install permanent black chain-link fencing around perimeter of sight - to start this week 1/11/23 and be complete by 1/18/23
Prepping place sidewalks and patio at back of site this week
Install site lighting Dash end of the month
Prep in place curb along fountain Street – end of month
Front paver install – end of month
Landscaping and planting - May 1, 2023