December 29th Construction Update

 
 

Summary Of Activities:

SITEWORK/MOBILIZE CONSTRUCTION SITE

(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)

TRUCKING/DELIVERIES

  • Minor deliveries will be ongoing

BUILDING ENVELOPE

  • Install lower and upper cornices

  • Install masonry at Fountain st elevation

  • Install Hardie panels at lower profiles

INTERIOR CONSTRUCTION

  • Drywall install and taping/sanding

  • Priming and painting

  • Flooring install

  • Cabinet Install

  • Elevator Install

SITEWORK

  • Prep and place sidewalk and curb along Fountain Street

  • Front paver install