October 17 Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
TRUCKING/DELIVERIES
Drywall deliveries ongoing
BUILDING ENVELOPE
Coping and final metal work on roof
Install siding at North and West elevations
Install masonry façade at North, West, and East elevations
INTERIOR CONSTRUCTION
Interior window caulking
In wall insulation at Level 2 and 5
Drywall install and taping/sanding at Level 3 and 4
SITEWORK
Retaining wall installation
Utility work on Regent Street (1 week remaining, expected to finish by 10/26)
Below is a snapshot of the northbound Regent Street detour. This detour will be in effect until the utility work on Regent Street finishes.