May 10th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.
SITEWORK/UTILITIES
Install Retaining Wall
SLAB ON GRADE
Install underground MEP/backfill underground
Prepare slab on grade for a concrete placement
STRUCTURAL WOOD FRAMING
Install load-bearing/exterior walls
Install 3rd-floor trusses
Install 3rd-floor sheathing
UPCOMING ACTIVITIES
Set retaining wall at the property line
*Street closures are forthcoming in the next couple of weeks. Specific dates and streets will be provided with next week’s construction up[date
TRUCKING/DELIVERIES
We are scheduled to have frequent wall panel deliveries upcoming and a large crane will be onsite for approximately the next 30 days.