May 10th Construction Update

 
 

Summary Of Activities:

SITEWORK/MOBILIZE CONSTRUCTION SITE

(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.

SITEWORK/UTILITIES

  • Install Retaining Wall

SLAB ON GRADE

  • Install underground MEP/backfill underground

  • Prepare slab on grade for a concrete placement

STRUCTURAL WOOD FRAMING

  • Install load-bearing/exterior walls

  • Install 3rd-floor trusses

  • Install 3rd-floor sheathing

UPCOMING ACTIVITIES

  • Set retaining wall at the property line

*Street closures are forthcoming in the next couple of weeks. Specific dates and streets will be provided with next week’s construction up[date

TRUCKING/DELIVERIES

We are scheduled to have frequent wall panel deliveries upcoming and a large crane will be onsite for approximately the next 30 days.

Previous
Previous

May 19th Construction Update

Next
Next

April 27th Construction Update