April 5th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.
SITEWORK/UTILITIES
Install Telecomm
STRUCTURAL STEEL
Deliver, unload, and shake out columns and beams.
Erect columns and beams
UPCOMING ACTIVITIES
Set precast block retaining wall
Install sanitary sewer line stub in.
Install storm water drainage system
TRUCKING/DELIVERIES
Steel delivery scheduled for 4/5