January 25th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.
ALL BLASTING HAS BEEN COMPLETED (YAY!)
Export blasted ledge material (Ongoing activity through blasting and until end of January)
Export soil to approved facilities (1/25-1/28)
Import gravel for foundation prep (through 1/28)
Foundation start date (1/24)
Form footings & walls for concrete (1/24)
First concrete pour for footing (1/28)
TRUCKING/DELIVERIES
During the activities above, trucking for offloading of soil/ledge will continue.
We will also have concrete trucks on-site for our concrete pours, exact amount will vary based
on the pour