August 26th Construction Update
Summary Of Activities:
SITEWORK/MOBILIZE CONSTRUCTION SITE
(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)
BUILDING ENVELOPE
Coping and final metal work on roof
Exterior blocking and siding install
Veneer brick install
Cornice install
INTERIOR CONSTRUCTION
Mechanical Electrical Plumbing/Fire Protection rough installation at all levels
In wall insulation
Drywall install level 4
SITEWORK
Retaining wall installation
Utility work on Regent St (targeting towards end of month)
TRUCKING/DELIVERIES
Drywall deliveries ongoing