February 24th Construction Update

 
 

Summary Of Activities:

SITEWORK/MOBILIZE CONSTRUCTION SITE

(Please note, highlighted signs in the plan above are NO STOPPING ANYTIME and cars parked there will be subject to towing as this whole street is needed for trucking operations. The plan above was put together and approved by the City of Boston for this project.)

SITEWORK/CONCRETE

  • Regrade at the back of the site (cuts/fills with existing soil)

  • Utility structure installations

  • Footing & Wall Foundations

    • Form foundation walls and install rebar

    • Form retaining walls

  • Upcoming activities: waterproof and backfill foundations

    TRUCKING/DELIVERIES

    We will have concrete trucks on site for our concrete pours, exact amount will vary based on the

    pour.